Pier 4 Phase Two
Slurry Wall Foundation, LBEs and nternal Bracing

Original Anthony's Pier 4 Restaurant in 1975 Slurry Plant Mobilization/Anthony's Demolition

Location: Boston, MA
Owner:
New England Development
Completion Date:
July, 2016
General Contractor:
Turner Construction Company
Vital Statistics:
Project Value: $
8,800,000.00
Wall Type: 30” Reinforced Concrete Wall, L
BEs
Wall Area:
65,000 S.F.
Max. Excavated Depth: 125

Project Description:
Anthonyís Famous Pier 4 Restaurant once welcomed celebrities like Liz Taylor and Frank Sinatra. As part of South Bostonís revitalization, a $500 million development project overlooking Boston Harbor is taking its place, featuring a thirteen-story office building, a nine-story residential building, and a three level underground parking garage. Much of the site was submerged until the late 1800ís when the pier was formed with dredged fill and organic soils. Due to the poor soil conditions and immediate proximity to the harbor, a braced slurry wall was chosen as the permanent foundation wall. Due to site access restrictions and delays in obtaining demolition permits for Anthonyís, the slurry wall was constructed in two phases, with a cement bentonite cutoff wall installed across the middle of the site, allowing an early start for mass excavation and bracing for the first phase. Deep load bearing elements (LBEs) were also constructed in lieu of spread footings to support some of the interior columns where soil conditions at subgrade were extremely poor.

Start of Mass Excavation with Slurry Wall Still Under Contruction

Return to Project Gallery page

 

 