What are the maximum unbraced vertical spans in slurry wall
foundation construction?

Typically, maximum unbraced vertical bracing spans are limited to 10’-15’. However, depending on the elevation of the water table, the thickness of the slurry wall and the amount of reinforcing steel, unbraced vertical spans can be increased
to about 25’. We have designed and installed post tensioned slurry walls for vertical spans in excess of 45’.

Back to FAQs page

 

 