500 Atlantic Avenue

Location: Boston, MA
Owner: Intell Boston Harbour, LLC
Completion Date: August, 2004
General Contractor: Bovis Lend Lease
Vital Statistics: Project Value: $1,500,000.00
Drilled Shaft Diameters:4’ and 6’
Shaft Depth: 90’

Project Description:
East Coast Slurry Company and A.A. Will Corporation teamed up to complete this foundation project for a 22 story mixed use building along Boston’s waterfront. Forty eight drilled shafts were installed by East Coast Slurry. Drilled shafts containing embedded steel columns were used as part of the time saving “top down” construction method. A.A. Will performed the top down mass excavation. Difficult site conditions were encountered due to existing wooden pile foundations which were installed as part of the old waterfront wharves.